Daikin EWAQ025BAWN [201/223] Field wiring

Daikin EWAQ032BAWN [201/223] Field wiring
Options ESIE11-05
190 Service Procedure
Field wiring 1. Connect the power supply wiring from the adaptor to the adaptor power supply connector on
the PCB of the outdoor module (as described in step 3 above).
2. Connect the transmission wiring to the F1 and F2 (OUT - OUT) terminal on the PCB. Use
double-core wiring with no polarity.
1 External control adaptor
2 PCB outdoor module
3. Using the delivered clamps, clamp the transmission wiring to the low voltage field wiring, etc.
Information Transmission wiring specifications
Sheathed wire (2 wires), 0.75~1.25 mm
2
Transmission wiring length
A transmission malfunction may occur if the following limits are exceeded.
- Total wiring length: Maximum 1000 m
- Number of branches: Maximum 16
4. If carrying out demand or low noise input, connect the adaptor terminals as shown in the
figure below.
1 Outside wiring
2 Host computer monitor panel or demand controller
DEMAND = Demand
LOW NOISE = Low noise
Demand input terminal
Short circuit between DEMAND 1 and C: As a guideline, demand should be about 70%.
Short circuit between DEMAND 2 and C: As a guideline, demand should be about 40%.
Short circuit between DEMAND 3 and C: Forced thermo off.
Low noise input terminal
When terminals are short-circuited during cooling, capacity save (unit fan turning at low
speed, compressor frequency control) is carried out. When terminals are short-circuited
during heating, capacity save (compressor frequency control) is carried out.
Use only at night when load is minimal.