Tecnoclima SUPERBESST 12 [31/40] First commissioning

Tecnoclima BESST/R 21 [31/40] First commissioning
31
PREPARATION FOR FIRST COMMISSIONING
The appliance first commissioning must be performed by the
manufacturer’s Technical Support Service.
Before commissioning the unit, make sure that:
– All safety conditions have been met
– The equipment has been correctly fixed to the supporting base
– The buffer area around the equipment has been observed
I The hydraulic connections have been made according to the
instruction manual
– The hydraulic system has been filled and vented
– The hydraulic circuit shut-off valves are open
– All electrical connections have been correctly made
– Voltage is included within a 10% tolerance with respect to the unit
nominal voltage
– The earth connection has been correctly made
– All electrical connections have been properly tightened
FIRST COMMISSIONING
NOTE FOR FIRST STARTUP:
FIRST COMMISSIONING
THE APPLIANCE MUST BE ALWAYS POWERED TO ENABLE CORRECT PRE-HEATING OF THE COMPRESOR OIL. THE
APPLIANCE MUST HAVE BEEN POWERED FOR AT LEAST EIGHT HOURS BEFORE THE FIRST STARTUP IS POSSIBLE.
After switching on the appliance:
- Turn OFF the main system circuit breaker
- Remove the inspection panel by undoing the four fixation screws
- Turn ON the main equipment switch “A
A
– Turn ON the main system circuit breaker)
– Make sure the display is on and showing the system return
water temperature
– Keep the unit powered but not working for at least two hours, so
that the compressor crankcase oil is heated
– switch on the appliance..
For the internal component locations, refer to the diagrams on
pages 9, 10, 11, 12, 13.