Airedale OptiChill OPC 750 [21/60] Locate and secure mount using bolting down holes 10 in base plate 2 ensure mounts are located in line with the unit base 3 if applicable remove compressor enclosure covers to allow access to mount fixing holes in the unit base 4 lock the upper retaining nuts 6a to the underside of the top plate 9 before a load is applied 5 remove retaining nut and washer 2 lower the unit onto the mounts and replace retaining nut and washer

Airedale OptiChill OPC 600 [21/60] Locate and secure mount using bolting down holes 10 in base plate 2 ensure mounts are located in line with the unit base 3 if applicable remove compressor enclosure covers to allow access to mount fixing holes in the unit base 4 lock the upper retaining nuts 6a to the underside of the top plate 9 before a load is applied 5 remove retaining nut and washer 2 lower the unit onto the mounts and replace retaining nut and washer
Chillers OPTICHILL
Chillers
Installation & Maintenance : 6564868 08/2008
21
Installation Data
ANTI VIBRATION MOUNTING (OPTIONAL)
Spring Type
Each mount is coloured to indicate the different loads, refer to AV selection sheet
supplied separately for correct allocation.
A
(1)
B C D E
mm 180 130 225 186 20 16
Dimensions
B
A
C
D
E
F
E
(1) Unloaded dimension
(2) For models with optional pumps fitted, please consult
Airedale.
Components
2
1
6a
5
6b
10
9
8
7
3
4
1 Locating Screw
2 Retaining Nut & Washer
3 Levelling Screw
4 Levelling Lock Nut
5 Retaining Studs
6a Upper Retaining Nuts
6b Lower Retaining Nuts
7 Spring assembly
8 Pressure Plate
9 Top Plate
10 Bolting-down holes
1 Locate and secure mount using bolting down holes (10) in base plate.
2 Ensure mounts are located in line with the unit base.
3 If applicable, remove compressor enclosure covers to allow access to mount fixing
holes in the unit base.
4 Lock the upper retaining nuts (6a) to the underside of the top plate (9) before a load
is applied.
5 Remove retaining nut and washer (2), lower the unit onto the mounts and replace
retaining nut and washer.
Installation
6 Beginning with the mount with the largest deflection, adjust the height of each mount
using the levelling screw (3).
CAUTION
Mountings must be adjusted incrementally in turn. Do not fully adjust 1 mount at a
time as this may overload and damage springs.
7 When all mounts are level, lock each into place using the levelling lock nut (4).
8 Lock all retaining nuts (6a and 6b) to the extreme ends of the retaining studs (5).
CAUTION
Do not connect any services until all anti vibration mounts have been
fully adjusted.
Pad Type
Components/Installation
1
2
3
2
5
4
3
6
7
1 M16 Bolt (Not Supplied)
2 Washer (Not Supplied)
3 Fixing Pad 506-063
4 A V Pad 506-062
5 2 x M16 Nut (Not Supplied)
6 Unit Base
7 Unit Mounting Plinth