Lowara LEZ 200-250 UNL 2204 [12/19] Model ler lers lez

Lowara LRZ 40-200 U 302 [12/19] Model ler lers lez
Installation, Operation and Maintenance Instruction
Model LER, LERS, LEZ
LER 100-english page 9
Revision 01
Article No 771073302
Issue 01/2010
If vibrations are transmitted to the pump
foundation from adjoining components, it must be
guarded through adequate vibration damping
paddings (vibrations from outside can impair the
bearing).
The size of these insulating pads will vary,
depending on circumstances, and should
there
fore be determined by an experienced
specialist.
Heavy pumps should be mounted on a concrete
foundation, which is isolated a
gainst the ground
with a min.
20 cm thick rubber- or cork plate.
5.2 Connection of Piping to the Pump
The pump must not be used as fixed point for
the piping. The permitted pip
ing loads must not
be exceeded, refer to chapter 3.6.
5.2.1 Suction and discharge pipe
The pipes must be of a size and design that liquid
can flow freely into the pump and that the pump
functions without problems. Particular attention is
to be paid to ensuring that suction pipes are
airtight and that the NPSH values are observed.
Under suction lift condition lays the suction pipe in
the horizontal section towards the pump so that it
is slightly inclined upwards so that no air traps
occur. Do not install fittings or elbows right before
the suction nozzle.
Piping for direct installation must show adequate
firmness. Keep in mind vibration insulation (see
chapter 5.1).
When laying the pipes, make sure that the pump
is accessible for maintenance, installation and
disassembly.
Notice "Permitted Forces on Flanges" (chapter
3.6).
Before connecting up to pump: remove protective
coverings from suction and discharge branches.
Before starting up, the pipe system, fittings and
equipment must be cleaned to remove weld
spatter, scale etc. Any pollutants are to be
completely removed from pump units that are
directly or indirectly connected to drinking water
systems before being installed and taken into use.
To protect the shaft sealing (especially mechanical
seals) against foreign impurities, it is
recommended that a sieve, 800 micron, is
installed in the suction / intake pipe when the
motor is being started up.
If the pipe system is tested with the pump
installed, do not exceed the maximum permitted
casing pressure of the pump and/or shaft sealing
(see data sheet).
When emptying the pipe after the pressure test,
make sure that the pump is treated properly
(danger of rust and problems when starting up).
5.3 Electric Connection
Electrical connection work may only be carri
ed
out by an authorised professional. The rules
and regulations valid for electrical technology,
especially those concerned with safety
meas
ures, must be observed. The regulations
of the national power supply companies
operating in that area must also be observed.
Before starting work, check that the information on the
motor name plate is the same as the local mains
network. The power supply cable of the coupled drive
motor must be connected up in accordance with the
wiring diagram produced by the motor manufacturer. A
protective motor switch must be provided.
In areas endangered to explosion IEC 60079-
14
must additionally be noticed for the electric
installation.
Standard connection:
5.4 Final check
It must be possible to turn the unit easily by hand at
the stub shaft.
6. Start-up, Operation, Shut down
The plant may only be started up by people who
are familiar with the local safety regulations and
with these Operating Instructions (especially
with the safety regulations and safety
instructions given here).
6.1 Initial start-up
Before starting up the pump, check, if the following
points were controlled and carried out:
There is no need to lubricate the pump before
starting it up.
Pump and suction pipe must be filled completely
with liquid when starting up.
At vertical installation position the seal chamber
must get vented before initial start-up.

Содержание

Похожие устройства

Скачать