SPECK Pumpen IN-VB-S 10-190 F [74/100] Decommissioning

SPECK Pumpen IN-VB 25-20 F [74/100] Decommissioning
Commissioning/Decommissioning
24 EN 11|2018
6.2 Decommissioning
For pre-requisites for shutting down the pump see "Switching the pump off" on page 23
NOTICE
For idle periods exceeding one year, elastomer components must be renewed.
NOTICE
The pump can only be replaced once it has been drained completely.
6.2.1 Pump/unit remains assembled
Switch the pump/unit on regularly – monthly to quarterly – during long idle periods. Switch the pump
back off again after approx. 1 minute.
This will avoid deposits forming in the pump/unit and piping system.
NOTICE
The pump/unit can be damaged if it runs dry!
Ensure that the pump/unit is always full of water.
6.2.2 Pump/unit is disassembled and stored
Drain pump/unit.
Clean and dry pump/unit.
Spray the interior of the pump with a preserving agent.
After treating the suction and discharge ports, close them using plastic caps.
Store pump/unit. See point 4.3 on page 16