Daikin REYQ96PATJ [15/22] 6 procedure for wiring inside units
![Daikin REYQ96PAYD [15/22] 6 procedure for wiring inside units](/views2/1718197/page15/bgf.png)
English 11
• When two wires are connected to a single terminal, connect them so
that the rear sides of the crimp contacts face each other. Also, make
sure the thinner wire is on top, securing the two wires simultaneously
to the resin hook using the included clamp (1).
7-6 Procedure for Wiring Inside Units
• Referring to figure 23, secure and wire the power and transmission
wiring using the included clamp (1), (2), and (3).
• Wire so that the ground wiring does not come into contact with the
compressor lead wiring.
If they touch, this may have an adverse effect on other devices.
•
The transmission wiring must be at least 2 in. away from the power wiring.
• Make sure all wiring do not contact to the pipes (hatching parts in the
figure 23).
(Refer to figure 23)
1. Secure to the hook of column support using the accessory
calmp (1).
2. Electric conduit
3. When routing out the power/ground wires from the left side.
4. When routing out the transmission wiring from the opening
for piping.
5. When routing out the power/ground wires from the front.
6. Clear over 2 in..
7. When routing out the transmission wiring from the knockout
hole.
8. When routing out the power/ground wires from the right side.
9. Power wiring
10. Ground wire
11. Transmission wiring
12. When wiring, exercise sufficient caution not to detach the
acoustic insulators from the compressor.
13. Secure to the back side of the support beam using the
accessory clamp (1).
14. Retain to the back of the column support with the accessory
clamp (2).
Precautions when knocking out knockout holes
• To punch out a knockout hole, hit it with a hammer.
• Open an appropriate hole as needed.
• After knocking out the holes trim off the burr, then we recommend
you to paint the edges and areas around the edges using the repair
paint to prevent rusting.
• Power line : Open a knockout hole as shown at left and connect
it using a conduit.
• Transmission line : Connect it using a conduit in the knockout hole
on the right.
NOTE
• After wiring work is completed, check to make sure there are no loose
connections among the electrical parts in the EL.COMPO.BOX.
8. AIR TIGHT TEST AND VACUUM DRYING
• After finished piping work, carry out air tight test and vacuum drying.
NOTE
• Always use nitrogen gas for the airtightness test.
• Absolutely do not open the shutoff valve until the main power ciruit
insulation measurement has been completed. (measuring after the
shutoff valve is opened will cause the insulation value to drop.)
<Needed tools>
<The system for air tight test and vacuum drying>
• Referring to figure 24, connect a nitrogen tank, refrigerant tank, and
a vacuum pump to the outside unit.
The refrigerant tank and the charge hose connection to refrigerant
charge port or the valve A in figure 24 are needed in “11. ADDI-
TIONAL REFRIGERANT CHARGE AND CHECK OPERATION”.
(Refer to figure 24)
1. Gauge manifold
2. Nitrogen
3. Measuring device
4. R410A tank (with siphon)
5. Vacuum pump
6. Charge hose
7. Refrigerant charge port
8. HP/LP gas pipe shutoff valve
9. Suction gas pipe shutoff valve
10. Liquid pipe shutoff valve
11. Valve A
12. Valve B
13. Valve C
14. Outside unit
15. To BS (or indoor) unit
16. Shutoff valve
17. Service port
18. Field piping
19. Gas flow
NOTE
• The air-tightness test and vacuum drying
should be done using the service ports of
equalizer pipe, HP/LP gas pipe, suction gas
pipe and liquid pipe shutoff valve.
See the [R410A] Label attached to the front
plate of the outside unit for details on the loca-
tion of the service port (see figure at right)
• See [Shutoff valve operation procedure] in
“11-1 Before working” for details on handling
the shutoff valve.
• The refrigerant charge port is connected to unit pipe.
When shipped, the unit contains the refrigerant, so use caution when
attaching the charge hose.
<Air tight test>
Pressurize the liquid pipe, suction gas pipe, HP/LP gas pipe and
equalizer pipe from the service ports of each shutoff valve to 550 psi
(do not pressurize more than 550 psi). If the pressure does not drop
within 24 hours, the system passes the test.
If there is a pressure drop, check for leaks, make repairs and perform
the airtight test again.
Terminal
block
Crip style
terminal
Wire : narrow
Wire : thick
Resin hook
Burr
Knockout hole
Left side Right side
Conduit
(field supply)
Lock nut
(field supply)
Conduit mounting plate
(accessory)
Gauge manifold
Charge hose
valve
• To prevent entry of any impurities and insure
sufficient pressure resistance, always use the
special tools dedicated for R410A.
• Use charge hose that have pushing stick for
connecting to service port of shutoff valves or
refrigerant charge port.
Vacuum pump
• The vacuum pump for vacuum drying should
be able to lower the pressure to –14.6 psi.
• Take care the pump oil never flow backward
into the refrigerant pipe during the pump stops.
[R410A] Label
Содержание
- Installation manual 1
- System air conditioner 1
- Figure 1 figure 3 figure 2 2
- Figure 11 2
- Figure 12 2
- Figure 4 figure 6 figure 5 2
- Figure 7 figure 8 figure 9 figure 10 2
- Figure 13 figure 14 3
- Figure 15 3
- Figure 16 figure 17 2 3
- Figure 17 1 3
- Figure 18 3
- Figure 19 3
- Figure 20 figure 22 3
- Figure 21 3
- Figure 23 4
- Figure 24 4
- Figure 25 4
- Figure 26 4
- Figure 27 figure 29 4
- Figure 28 4
- Figure 30 4
- Figure 31 4
- 1 safety considerations 5
- Contents 5
- English 1 5
- First of all 5
- 2 special notice of product 6
- English 6
- 1 combination 7
- 2 standard supplied accessories 7
- 3 disposal requirements 7
- 3 option accessory 7
- 4 technical and electrical specifications 7
- 5 main components 7
- English 3 7
- Introduction 7
- Selection of location 7
- 1 selection of piping material and refrigerant branching kit 8
- 1 selection of piping material and refrigerantbranching kit 8
- English 8
- Inspecting and handling the unit 8
- Placing the unit 8
- Refrigerant piping 8
- 2 protection against contamination when installing pipes 9
- 2 protection against contaminationwhen installing pipes 9
- 3 pipe connection 9
- 4 connecting the refrigerant piping 9
- English 5 9
- 1 indicate the outside unit multi connection piping kit 2 in case of multi outdoor system re read outside unit to the first outside unit multi connection piping kit as seen from the indoor unit 10
- 5 example of connection 10
- Actual and equivalent pipe length 10
- Actual pipe length 10
- Actual pipe length equivalent length 10
- Actual pipe length from first refrigerant branch kit either refnet joint or refnet header to indoor unit 130 ft note 2 example 8 b c d e s 130 ft 10
- Allowable length after the branch 10
- Between outside unit 2 and indoor unit 10
- Bold 3 pipes 10
- Branch with refnet joint branch with refnet joint and header branch with refnet header 10
- Bs unit 10
- Difference in height between outside unit and indoor unit h1 164 ft max 130 ft if the outside unit is below difference in height between adjacent indoor units h2 49 ft difference in height between adjacent outside units h3 16 ft 10
- English 10
- Example 6 b 130 ft 8 m n p 130 ft example 8 o 10
- Example 8 a o 10
- Example of connection connection of 8 indoor units 10
- First outside unit multi connection piping kit 10
- Ft equivalent pipe length between outside unit 2 and indoor unit 620 ft note 1 10
- Indoor unit cool heat selection possible 10
- Indoor unit cooling only 10
- Indoor unit side 2 pipes 10
- Multi outside system 10
- Outside unit 10
- Outside unit outside unit 10
- Outside unit side 3 pipes 10
- Pipe length between outside unit 2 and indoor unit 540 ft example 8 a b c d e 540 ft 10
- Piping from bs unit to indoor unit or piping from refrigerant branch kit to indoor unit used as cooling only 10
- Piping from outside unit to bs unit 10
- Single outside system 10
- Suction gas pipe hp lp gas pipe liquid pipe 10
- Suction gas pipe liquid pipe 10
- Thin 2 pipes 10
- Total piping length from outside unit 2 to all indoor unit 3280 ft actual pipe length from first outside unit multi connection piping kit to outside unit 33 ft equivalent pipe length from first outside unit multi connection piping kit to outside unit 43 ft 10
- English 7 11
- Outside unit multi connection piping kit and refrigerant branch kit selection 11
- Pipe size selection 11
- 0 75 1 0 21 1 0 81 75 0 40 10 0 15 1 2 2 1 12
- 11 82 11 lb 12
- A b 2 c 2 d 2 e 2 f 2 g 2 h i j k l m n p 3280 ft 12
- A b u r c n s t o p 12
- English 12
- How to calculate the additional refrigerant to be charged 12
- If available on the site use this size otherwise it can not be increased 12
- Increase the pipe size as follows 12
- Indoor units 1 8 12
- Outside unit refnet joint a g 12
- Required conditions example drawings 12
- Round off in units of 0 lb 12
- The farthest indoor unit 8 the nearest indoor unit 1 12
- Φ 3 8 φ 1 2 φ 1 2 φ 5 8 φ 5 8 φ 3 4 φ 3 4 φ 7 8 φ 7 8 φ 1 φ 1 1 8 φ 1 1 4 φ 1 3 8 φ 1 1 2 12
- 1 power circuit safety device and cable requirements 13
- 1 power circuit safety device and cablerequirements 13
- 2 wiring connection example for whole system 13
- 3 leading wire procedure 13
- English 9 13
- Field wiring 13
- 4 transmission wiring connection procedure 14
- 5 power wiring connection procedure 14
- Crimp style terminal 14
- Cup washer 14
- Cut out section 14
- English 14
- Power wire crimp style terminal 14
- 6 procedure for wiring inside units 15
- Air tight test and vacuum drying 15
- English 11 15
- R410a label 15
- Resin hook 15
- Terminal block crip style terminal wire narrow wire thick 15
- 1 before working 16
- Additional refrigerant charge and check operation 16
- Additional refrigerant chargeand check operation 16
- Checking of device and installa tion conditions 16
- Checking of device and installationconditions 16
- English 16
- Pipe insulation 16
- 2 procedure of adding refrigerant charging and check operation 17
- 2 procedure of adding refrigerant charging andcheck operation 17
- English 13 17
- H h i h h h h 17
- J h h h h h h 17
- J h h h i h i 17
- J h h i h h h 17
- J h j h j j h 17
- 2 1 procedure of adding refrigerant charging 18
- Cooling mode 18
- English 18
- H h i h h h h 18
- Heating mode 18
- Less than above range 18
- Outdoor temp 32 f db 109 f db indoor temp 50 f db 90 f db 18
- English 15 19
- 1 before test run 20
- 2 2 procedure of check operation 20
- 2 test run 20
- English 20
- Onsite settings 20
- Test run 20
- 3 checks after test run 21
- Caution for refrigerant leaks 21
- English 17 21
- P215731 8m em09a062a 22
Похожие устройства
- Daikin REYQ72PATJ Инструкция по монтажу
- Daikin REYQ120PATJ Спецификация
- Daikin REYQ120PATJ Руководство по вводу в эксплуатацию
- Daikin REYQ120PATJ Инструкция по монтажу
- Daikin REYQ120PATJ Инструкция по монтажу
- Daikin REYQ192PATJ Спецификация
- Daikin REYQ168PATJ Спецификация
- Daikin REYQ168PATJ Руководство по вводу в эксплуатацию
- Daikin REYQ192PATJ Руководство по вводу в эксплуатацию
- Daikin REYQ192PATJ Инструкция по монтажу
- Daikin REYQ168PATJ Инструкция по монтажу
- Daikin REYQ144PATJ Спецификация
- Daikin REYQ144PATJ Руководство по вводу в эксплуатацию
- Daikin REYQ144PATJ Инструкция по монтажу
- Daikin REYQ72PAYD Спецификация
- Daikin REYQ72PAYD Руководство по вводу в эксплуатацию
- Daikin REYQ72PAYD Инструкция по монтажу
- Daikin REYQ96PAYD Спецификация
- Daikin REYQ96PAYD Руководство по вводу в эксплуатацию
- Daikin REYQ96PAYD Инструкция по монтажу