4.3 Position of the terminal box
The terminal box must not point downwards as otherwise water
may penetrate easily.
Before installing the pump, the terminal box can be turned by
90° in each case. To do this, undo the casing’s 4 screws and turn
the motor head to the required terminal box position.
Do not shift or damage the seal between the motor and pump casing.
After inserting the screws, tighten them up diagonally.
english
21
4.1 Flushing out the heating system (with pump removed)
In order to avoid undesirable interruptions in operation
and non-starting of the pump after long periods of standstill,
it is recommended for a newly-installed or converted heating
system that the system be drained, flushed through well
and then refilled again after heating up for the first time.
The system must comply with the latest state of technology.
(Positioning of expansion vessel or initial safety feed.)
3. Intended application
Biral circulation pumps of the series
L
(single pumps) and
LD
(twin pumps)
are used to circulate liquids in
– hot-water heating systems
– closed-circuit industrial circulating systems.
They are glandless and not suitable for secondary
hot water services.
Heating water in accordance with VDI 2035, water/glycol mixture
with up to 50% glycol proportion. The pumps may not be used
in the food-processing industry nor for drinking water.
3.1 Operating temperature/Operating pressure
Permissible water temperature: –20 °C to +140 °C
Permissible operating pressure: max. 6 bar
Special versions (PN 16): max. 16 bar
Check the unit’s permissible operating pressure
Ambient temperature: max. 40 °C
Noise level: < 70 dB (A)
4. Assembly
4.2 Antifreezers (as far as necessary)
Important: Flush the piping network through particularly well
before the antifreeze mixture is filled.
Follow the antifreeze supplier’s instructions with respect to mixing
and filling, as well as the choice of material in the piping and
apparatus network (pay particular attention to protection against
corrosion!). Water/glycol mixture up to 50% glycol ratio permissible.
Over 10% glycol ratio, correct the pumping data of the pumps
accordingly.
2. Transport/Storage
The pumps are supplied from the factory in appropriate packing.