The Schedule function allows users to set a starting point or time period for a task. For example, a pump needs
to start at 9: 00 PM and stop at 11:00 PM every Monday, Wednesday, and Friday.
Select the IF condition to Schedule and click on the property button ( ) to enter the setting window.
For recurrent actions, select the Recurrence checkbox and select the week days. If there a time period needs
to be defined, specify the stop date in the range column.