WARNING
▪ After finishing the electrical work, confirm that each
electrical component and terminal inside the electrical
components box is connected securely.
▪ Make sure all covers are closed before starting up the
unit.
NOTICE
Only applicable if the power supply is three‑phase, and the
compressor has an ON/OFF starting method.
If there exists the possibility of reversed phase after a
momentary black out and the power goes on and off while
the product is operating, attach a reversed phase
protection circuit locally. Running the product in reversed
phase can break the compressor and other parts.
3.2.5 Gas
The gas boiler is factory‑set to:
▪ the type of gas quoted on the type identification plate or on the
setting type identification plate,
▪ the gas pressure quoted on the type identification plate.
Operate the unit ONLY with the gas type and gas pressure indicated
on these type identification plates.
Installation and adaptation of the gas system MUST be conducted
by:
▪ personnel qualified for this work,
▪ in compliance with valid gas installation related guidelines,
▪ in accordance with applicable regulations of the gas supply
company,
▪ In accordance with local and national regulations.
Boilers that use natural gas MUST be connected to a governed
meter.
Boilers that use liquid petroleum gas (LPG) MUST be connected to a
regulator.
The size of the gas supply pipe should under no circumstance be
less than 22mm.
The meter or regulator and pipe work to the meter MUST be
checked preferably by the gas supplier. This is to ensure that the
equipment works good and meets the gas flow and pressure
requirements.
DANGER
If you smell gas:
▪ call immediately your local gas supplier and your
installer,
▪ call the suppliers's number on the side of the LPG tank
(if applicable),
▪ turn off the emergency control valve at the meter/
regulator,
▪ do NOT turn electrical switches ON or OFF,
▪ do NOT strike matches or smoke,
▪ put out naked flames,
▪ open doors and windows immediately,
▪ keep people away from the affected area.
3.2.6 Gas exhaust
Flue systems must NOT be modified or installed in any way other
than as described in the fitting instructions. Any misuses or
unauthorized modifications to the appliance, flue or associated
components and systems could invalidate the warranty. The
manufacturer accepts no liability arising from any such actions,
excluding statutory rights.
It is NOT allowed to combine flue system parts purchased from
different suppliers.
3.2.7 Local legislation
See the local and national regulations.
Local regulations for UK
It is law that all gas appliances are installed by a gas safe registered
competent engineer and in accordance with the following
recommendations:
▪ Current Gas Safety (Installation and Use) Regulations
▪ All current building regulations
▪ Building Standards (Scotland) Consolidated
▪ This appliance MUST be installed in accordance with the Gas
(Safety and Use) Regulations, current Building Regulations,
Building Standards (Scotland), I.S.813 Installation of Gas
Appliances (Ireland), IEE Wiring Regulations (BS 7671), Health
and Safety Document No. 635 (Electricity at Work Regulations)
and Local Water Authority Bye Laws
▪ UK Water Regulations and Bye Laws
▪ Health & Safety
The installation MUST comply with the following British Standards
codes of practice:
▪ BS 5440-1: 2008 Flueing and ventilation for gas appliances of
rated input not exceeding 70 kW net (1st, 2nd and 3rd family
gases)
▪ BS 5440-2: 2009 Flueing and ventilation for gas appliances of
rated input not exceeding 70 kW net (1st, 2nd and 3rd family
gases)
▪ BS 5546: 2010 Specification for installation and maintenance of
gas-fired water-heating appliances of rated input not exceeding
70kW net
▪ BS 5549: 1990 Forced circulation hot water systems.
▪ BS 6700: 2006 + A1: 2009 Design, installation, testing and
maintenance of services supplying water for domestic use within
buildings and their curtilages - Specification
▪ BS 6798: 2014 Specification for selection, installation, inspection,
commissioning, servicing and maintenance of gas-fired boilers of
rated input not exceeding 70kW net
▪ BS 6891: 2015 Specification for the installation and maintenance
of low pressure gas installation pipework of up to 35mm (R1¼) on
premises
▪ BS 7593: 2006 Code of practice for treatment of water in domestic
hot water space heating systems
▪ BS 7671: 2018 Requirements for electrical installations. IET wiring
regulations
▪ BS 7074: 1 Code of practice for domestic and hot water supply
▪ EN12828: 2014 Space heating for domestic premises
Potable water: all seals, joints and compounds (including flux and
solder) and components used as part of the secondary domestic
water system MUST be approved by WRAS.
Содержание
- Daikin altherma h hybrid gas boiler module p.1
- Installation and operation manual p.1
- Ehy2komb28aa ehy2komb32aa p.1
- Ehy2komb28aa ehy2komb32aa p.2
- Director p.2
- Daikin tcf red 04 p.2
- Daikin tcf gar 01 p.2
- Daikin europe n v p.2
- Boiler efficiency 92 42 eec p.2
- Radio equipment 2014 53 eu p.2
- P369568 6j p.2
- Ostend 14th of march 2019 p.2
- Low voltage 2014 35 eu p.2
- Kiwa nb0063 p.2
- Installation and operation manual p.2
- Hiromitsu iwasaki p.2
- Gr0508 p.2
- Gas appliance regulation 2016 426 eu p.2
- En15502 1 2012 a1 2015 en60335 2 102 2016 en55014 1 2017 en55014 2 2015 en61000 3 2 2014 en61000 3 3 2013 etsi en300220 1 v3 etsi en300220 2 v3 p.2
- Benchmark places responsibilities on both manufacturers and installers the purpose is to ensure that customers are provided with the correct equipment for their needs that it is installed commissioned and serviced in accordance with the manufacturer s instructions by competent persons and that it meets the p.3
- About the units and options 9 p.3
- About the product 3 p.3
- Troubleshooting 35 p.3
- About the product p.3
- The benchmark scheme p.3
- About the documentation 4 p.3
- Technical data 38 p.3
- About the box 8 p.3
- Table of contents p.3
- Operation 31 p.3
- Maintenance and service 32 p.3
- Installation 12 p.3
- Glossary 37 p.3
- General safety precautions 4 p.3
- Especially for uk p.3
- Disposal 45 p.3
- Configuration 25 p.3
- Commissioning 32 p.3
- General safety precautions p.4
- About this document p.4
- About the documentation p.4
- Meaning of warnings and symbols p.4
- Installation site p.5
- General safety precautions p.5
- General p.5
- For the installer p.5
- General safety precautions p.6
- Electrical p.6
- Local legislation p.7
- General safety precautions p.7
- Gas exhaust p.7
- To unpack the gas boiler p.8
- To remove the accessories from the gas boiler p.8
- Symbols on the package p.8
- Gas boiler p.8
- About the box p.8
- About the units and options p.9
- Possible options for the gas boiler p.9
- Identification label gas boiler p.9
- Identification p.9
- Combining units and options p.9
- About the units and options p.10
- About the units and options p.11
- To open the switch box cover of the gas boiler p.12
- To open the gas boiler p.12
- To install the gas boiler p.12
- Opening the unit p.12
- Mounting the gas boiler p.12
- Installation space requirements p.12
- Installation space p.12
- Installation p.12
- To install the condensate trap p.13
- Installation p.13
- To connect the water piping for domestic hot water not applicable for switzerland p.14
- Internal connections p.14
- Installation p.14
- External connections p.14
- Connecting water piping p.14
- Connecting the water piping of the gas boiler p.14
- Condensate pump p.14
- Condensate pipe work p.14
- To fill the domestic water circuit of the gas boiler p.15
- To connect the water piping for space heating p.15
- To connect the water piping for domestic hot water applicable for switzerland p.15
- Installation p.15
- Flow resistance graph for appliance domestic hot water circuit p.15
- Connecting the electrical wiring p.15
- Installation p.16
- Connecting the gas piping p.16
- To connect the main power supply of the gas boiler p.16
- To connect the gas pipe p.16
- To connect the electrical wiring to the gas boiler p.16
- To change the gas boiler to 80 125 concentric connection p.17
- To change the 60 100 concentric connection to a dual pipe connection p.17
- Installation p.17
- Connecting the boiler to the flue gas system p.17
- Installation p.18
- Calculate the total piping length p.18
- Appliance categories and pipe lengths p.18
- Installation p.19
- Installation p.20
- Installation p.21
- Flue pipe position p.21
- Applicable materials p.21
- Fitting a horizontal flue system p.22
- Plume management kit p.22
- Insulation of the gas exhaust and air intake p.22
- Installation p.22
- Fitting a vertical flue system p.22
- Installation p.23
- Flues in voids p.23
- Flue gas materials c63 available on the market p.23
- About securing the flue system p.23
- Installation p.24
- 3 50 mm m p.24
- 1000 mm p.24
- Overview configuration p.25
- Gas boiler p.25
- Finishing the gas boiler installation p.25
- Configuration p.25
- Basic configuration p.25
- To turn on off the gas boiler p.25
- To perform an air purge on the gas supply p.25
- To install the cover plate p.25
- To close the gas boiler p.25
- To set the parameters via the service code p.26
- To reset the gas boiler p.26
- Maximum space heating supply temperature p.26
- Keep hot function p.26
- Frost protection function p.26
- Domestic hot water temperature p.26
- Domestic hot water comfort function p.26
- Configuration p.26
- Configuration p.27
- Maximum space heating power setting p.28
- Frost protection function p.28
- Configuration p.28
- To change to a different type of gas p.29
- Configuration p.29
- About the co ₂ setting p.29
- Configuration p.30
- Overview operation p.31
- Operation modes p.31
- Operation p.31
- Heating p.31
- Domestic hot water p.31
- To perform a test run on the gas boiler p.32
- To perform a gas pressure test p.32
- To disassemble the gas boiler p.32
- Opening the gas boiler p.32
- Maintenance safety precautions p.32
- Maintenance and service p.32
- Commissioning p.32
- Maintenance and service p.33
- To clean the inside of the gas boiler p.34
- To assemble the gas boiler p.34
- Maintenance and service p.34
- Troubleshooting p.35
- Symptom the burner ignites noisily p.35
- Symptom the burner does not ignite p.35
- Solving problems based on symptoms p.35
- Precautions when troubleshooting p.35
- General guidelines p.35
- Symptom no domestic hot water p.36
- Symptom hot water does not reach the temperature tank installed p.36
- Symptom hot water does not reach the temperature no tank installed p.36
- Solving problems based on error codes p.36
- Error codes overview p.36
- Error codes of the gas boiler p.36
- Troubleshooting p.36
- Symptom the power is reduced p.36
- Symptom the burner resonates p.36
- Symptom space heating does not reach the temperature p.36
- Symptom no space heating by the gas boiler p.36
- Glossary p.37
- Technical data p.38
- Components gas boiler p.38
- Components p.38
- Bottom view p.38
- A subset of the latest technical data is available on the regional daikin website publicly accessible the full set of latest technical data is available on the daikin business portal authentication required p.38
- Wiring diagram p.39
- Technical specifications gas boiler p.39
- Technical specifications p.39
- Technical data p.39
- General p.39
- Wiring diagram gas boiler p.39
- Technical data p.40
- Energy related products specifications p.40
- Technical data p.41
- Gas category and supply pressure p.41
- Technical data p.42
- This commissioning checklist is to be completed in full by the competent person who commissioned the boiler as a means of demonstrating compliance with the appropriate building regulations and then handed to the customer to keep for future reference p.43
- Technical data p.43
- Installation and operation manual p.43
- Gas boiler system commissioning checklist p.43
- Ehy2komb28 32aa daikin altherma h hybrid gas boiler module 4p538953 1a 2020 2 p.43
- Service 01 p.44
- P538953 1a 2020 2 p.44
- Installation and operation manual p.44
- Ehy2komb28 32aa p.44
- Daikin altherma h hybrid gas boiler module p.44
- Technical data p.44
- Service record p.44
- Service 10 p.44
- Service 09 p.44
- Service 08 p.44
- Service 07 p.44
- Service 06 p.44
- Service 05 p.44
- Service 04 p.44
- Service 03 p.44
- Service 02 p.44
- Disposal p.45
Похожие устройства
-
Daikin EVLQ08CAV3Руководство по применению для установщика -
Daikin EVLQ08CAV3Справочное руководство для монтажника -
Daikin EVLQ08CAV3Общие правила техники безопасности -
Daikin EVLQ08CAV3Инструкция по монтажу -
Daikin EVLQ05CAV3Справочное руководство для монтажника -
Daikin EVLQ05CAV3Руководство по применению для установщика -
Daikin EVLQ05CAV3Общие правила техники безопасности -
Daikin EVLQ05CAV3Инструкция по монтажу -
Daikin EHYKOMB33AA3Справочное руководство для монтажника -
Daikin EHYKOMB33AA3Руководство по применению для установщика -
Daikin EHYKOMB33AA3Руководство по эксплуатации -
Daikin EHYKOMB33AA2Руководство по применению для установщика
Узнайте о важных мерах безопасности при установке и эксплуатации газовых котлов. Следуйте рекомендациям для безопасной работы и предотвращения аварий.