14.5 Pressure Relief Valve/s
1. Pressure relief valves are preset to discharge at a set pressure dependant on placement within the circuit. No
attempt should be made to adjust this setting or to check the setting by discharging the valve. Valves should be
removed before testing to a value in excess of 80% of the valve setting.
2. Should the need to replace a valve arise, this can be achieved by shutting off the faulty valve by either removing
the system charge on assemblies fitted with single relief valves or via a dual shut off valve assembly in which the
pressure relief valve is mounted.
3. During installation of the pack the pipework from the pressure relief valves should be run out of the building and
vented safely into the atmosphere. No restriction such as pipe caps Etc. should be left in or on the pipework
leading from the pressure relief valves to the outside as any back pressure will change the relief set point of the
valves. Pipe-work should be sized to provide correct discharge flow rate for system design.
4. Relief valves that have been found to have discharged refrigerant should be replaced as positive sealing after
discharge is not guaranteed.
5. During maintenance checks a leak test should be carried out in case of seeping occurring.
Pressure Relief Valve Testing and Replacement
Inspect the valves and Replace regularly as per the PED and relevant regulations
14.6 Pressure switches and transducers
Transducers
Transducers that incorporate Schrader depressors will be supplied fitted directly to a port, those without will
include a valve for isolation purposes to allow for maintenance.
Pressure switches Safety.
Pressure switches fitted to compressor bodies are pre-set cartridge type will NOT be fitted with Schrader valves;
this is to ensure that these safety switches are reacting to a definite pressure that cannot be influenced by
mechanical tolerances.
High Pressure switch testing
Periodically, as deemed by customer requirements, remove the high pressure switch from the system and apply
dry nitrogen pressure using a calibrated gauge of a suitable range and ensure that the switch breaks and resets in
line with the settings shown on the switch data sheet. Refit the switch, leak test and set the system back in
operation.
15 Maximum refrigerant charge
When the unit is pumped down, the receiver must be capable to accommodate all the refrigerant charge (kg)
holding in the system. Also, it is really important to avoid to overcharge the system which can cause issues in
compressor operation and efficiency.
Consindering the above, the estimation of maximum refrigerant charge values are based on 80% capacity of the
receiver (assuming that the unit is pumped down from the receiver).
The maximum amount of refrigerant can be charged into the system is 14 kg.
Page 23 of 177
Copyright HPL January 2021
P4115S Rev 02