Removing and installing main
(centre) stand
Remove the sump guard.
Secure stand, BMWNo.001520, to motorcycle
with overlength bushes and screws,
BMW No. 00 1 527.
L Note:
Mount a washer on the screw on the right as viewed
in the forward direction of travel.
Depth of thread in tapped bore has been reduced!
Disconnect tension springs.
Remove machine screws (1) in bearing
bushings (2).
Remove right and left bearing bushings (2).
Disconnect the plug from the side stand switch.
Remove the main (centre) stand.
Remove right and left bearing blocks (2).
Installation is the reverse of the removal proce-
dure.
L Note:
When installing the springs, make sure that the thick
spring is on the inside and the thin spring on the
outside (arrow).
Lubricant:
for pivot bushings.............. Staburags NBU 30 PTM