Daikin RKS60E3V1B [137/150] Pump down operation

Daikin FDKS25EAVMB [137/150] Pump down operation
SiBE07-618_D Pump Down Operation
Trial Operation and Field Settings 127
1. Pump Down Operation
Outline In order to protect the environment, be sure to conduct pump down operation when relocating or
disposing the unit.
Detail 1) Remove the valve caps from the liquid stop valve and the gas stop valve.
2) Carry out forced cooling operation.
3) After 5 to 10 minutes, close the liquid stop valve with a hexagonal wrench.
4) After 2 to 3 minutes, close the gas stop valve and stop the forced cooling operation.
Refer to page 128 for forced cooling operation.
Gas stop valve
Valve cap
Hexagonal
wrench
Close
Liquid stop valve
Service port
(R13628)