Daikin GCU2040PXB1 Инструкция по монтажу онлайн [19/177] 610032

Daikin GCU2040PXB1 Инструкция по монтажу онлайн [19/177] 610032
4. All cable connections are tight.
5. Motor starter controls/contactor overloads are set correctly.
6. Check all contactors operate correctly.
13.6 Operational Checkout
When the system has been charged and has operated for at least 2 hours at normal operating conditions without
any indication of malfunction, it should be allowed to operate overnight on automatic controls. Then a thorough re-
check of the entire system operation should be made as follows:
1. Check the unit head and suction pressures. If the pressures are not within the system design limits, determine
why and take corrective action.
2. Check the liquid line sight-glass and expansion valves operation. If there are indications that more refrigerant is
required, leak test all connections and system components and repair any leaks before adding refrigerant.
3. Expansion valves must be checked for proper superheat settings.
Expansion valve probes must be in positive thermal contact with suction lines.
Valves with high superheat settings produce little refrigeration and poor oil return.
Too little superheat causes low refrigerant capacity and promotes liquid slugging and compressor oil removal.
LIQUID REFRIGERANT MUST BE PREVENTED FROM REACHING THE COMPRESSOR.
4. Using suitable instruments carefully check line voltage and amperages at the compressor terminals. Voltage
should be within 10% of the nameplate voltage.
The current should not exceed that on the nameplate rating. If amperage draw is excessive, immediately
determine the cause and take corrective action. On three phase motor-compressor, check to see that a balanced
load is drawn by each phase. Check all fan motors on air-cooled condensers and in fixture evaporator coils for
correct rotation. Fan motor mounts and fan blades should be carefully checked for tightness and proper alignment.
All motors requiring lubrication should be oiled or greased as per manufacturer’s recommendations. Check all
electrical load bearing terminals for tightness.
5. When this stage is reached, the unit can now be left running on full automatic operation, commissioning sheets
checked and completed (Section 9). The plant should be allowed to run for a further few days and then a further
check made of all controls and any minor adjustments made.
6. The hints and procedures on commissioning are based on experience to date and checks made of units running
during both winter and summer periods. Do ensure that the settings of the components are correct before making
any adjustments.
7. DO NOT adjust components without satisfying yourself that there is good reason to do so. If adjustments are
carried out, record the final setting on the commissioning report.
13.5.1 Compressor bypass valve
Please refer to P&ID for compressor bypass valve position. The role of bypass valve is very critical for the rotary
compressor operation especially when the compressor is getting the signal to run. The valve is fully open when the
unit is switched off. This valve ensures the pressure balance between interstage and first-stage suction of the
compressor. That helps the compressor to start smothly.
13.7Lubrication Oil Condition (guide)
Complete system oil change is not needed. Additional oil charge and more information can be found in oil charge
section.
14.
Service and Maintenance
The following notes are not designed as a definitive guide, the maintenance procedures should be applied in
conjunction with your companies work instructions and working practises. Any further information not covered by
this section may be obtained from Hubbard Products Ltd on request.
Page 19 of 177
Copyright HPL January 2021
P4115S Rev 02

Содержание

Скачать