Commissioning/Decommissioning
24 EN 11|2018
6.2 Decommissioning
For pre-requisites for shutting down the pump see "Switching the pump off" on page 23
NOTICE
For idle periods exceeding one year, elastomer components must be renewed.
NOTICE
The pump can only be replaced once it has been drained completely.
6.2.1 Pump/unit remains assembled
Switch the pump/unit on regularly – monthly to quarterly – during long idle periods. Switch the pump
back off again after approx. 1 minute.
This will avoid deposits forming in the pump/unit and piping system.
NOTICE
The pump/unit can be damaged if it runs dry!
Ensure that the pump/unit is always full of water.
6.2.2 Pump/unit is disassembled and stored
Drain pump/unit.
Clean and dry pump/unit.
Spray the interior of the pump with a preserving agent.
After treating the suction and discharge ports, close them using plastic caps.
Store pump/unit. See point 4.3 on page 16
Содержание
- In vb in vb s p.1
- Inhaltsverzeichnis p.5
- Glossar p.8
- Umgang mit dieser anleitung p.9
- Mitgeltende dokumente p.9
- Zu diesem dokument p.9
- Zielgruppe p.9
- Unvollständige maschine p.9
- Bestimmungsgemäße verwendung p.10
- Sicherheitsvorschriften p.10
- Sicherheit p.10
- Personalqualifikation p.10
- Schutzeinrichtungen p.11
- Schilder p.11
- Restrisiken p.11
- Bauliche veränderungen und ersatzteile p.11
- Vermeidung von sachschäden p.12
- Störungen p.12
- Beschreibung p.14
- Benennung p.14
- Funktion p.14
- Typenschild p.15
- Ausführung p.15
- Produktinformationen gemäß verordnung 547 2012 für wasserpumpen mit maximaler wellenleistung von 150 kw zur richtlinie 2009 125 eg öko design richtlinie p.16
- Pumpe anheben p.17
- Transport und zwischenlagerung p.17
- Transport p.17
- Rücksendung p.18
- Lagerung p.18
- Rohrleitungen p.19
- Installation p.19
- Einbauort p.19
- Aufstellung p.20
- Elektrischer anschluss p.21
- Drehrichtung prüfen p.21
- Überlastschutzeinrichtung p.22
- Inbetriebnahme außerbetriebnahme p.23
- Inbetriebnahme p.23
- Außerbetriebnahme p.26
- Übersicht p.27
- Störungen p.27
- Wartung während des betriebes p.29
- Wartung instandhaltung p.29
- Schmierung p.29
- Instandhaltungsarbeiten p.29
- Entleeren p.30
- Demontage der pumpe anlage p.30
- Pumpe anlage montieren p.34
- Schraubenanzugsmomente p.36
- Gewährleistung p.37
- Ersatzteile p.37
- Entsorgung p.38
- Maßzeichnung 10 maßzeichnung p.39
- In vb s v p.39
- In vb s f p.39
- In vb s p.39
- 2018 de 37 p.39
- Technische daten p.39
- Technische daten p.40
- De 11 2018 p.40
- Technische daten p.41
- 2018 de 39 p.41
- Technische daten p.42
- De 11 2018 p.42
- Technische daten p.43
- 2018 de 41 p.43
- Technische daten p.44
- De 11 2018 p.44
- Technische daten p.45
- 2018 de 43 p.45
- Schnittzeichnung p.46
- En translation of original operation manual in vb in vb s p.51
- Table of contents p.53
- Glossary p.56
- Using this manual p.57
- Target group p.57
- Other applicable documents p.57
- Incomplete machine p.57
- About this document p.57
- Safety regulations p.58
- Safety p.58
- Personnel qualification p.58
- Intended use p.58
- Structural modifications and spare parts p.59
- Residual risk p.59
- Protective equipment p.59
- Preventing material damage p.60
- Faults p.60
- Description p.62
- Function p.62
- Designation p.62
- Name plate p.63
- Design p.63
- Product information according to 547 2012 for water pumps with a maximum shaft performance of 150 kw for the 2009 125 eg standard eco design guidelines p.64
- Transport and intermediate storage p.65
- Transport p.65
- Lifting the pump p.65
- Storage p.66
- Returns p.66
- Installation p.67
- Installation site p.67
- Installation p.68
- Electrical connection p.69
- Check the direction of rotation p.69
- Current p.70
- Overload protection device p.70
- Commissioning decommissioning p.71
- Commissioning p.71
- Decommissioning p.74
- Overview p.75
- Faults p.75
- Maintenance work p.77
- Maintenance during operation p.77
- Maintenance p.77
- Lubrication p.77
- Draining p.78
- Disassembling of the pump unit p.78
- Assembling pump unit p.82
- Screw tightening torque p.84
- Warranty p.85
- Spare parts p.85
- Disposal p.86
- Technical data p.87
- In vb s v p.87
- In vb s f p.87
- In vb s p.87
- Dimensional drawing 10 dimensional drawing p.87
- 2018 en 37 p.87
- Technical data p.88
- En 11 2018 p.88
- Technical data p.89
- 2018 en 39 p.89
- Technical data p.90
- En 11 2018 p.90
- Technical data p.91
- 2018 en 41 p.91
- En 11 2018 p.92
- Technical data p.92
- Technical data p.93
- 2018 en 43 p.93
- Sectional drawing p.94
- Eg konformitätserklärung p.100
Похожие устройства
-
SPECK Pumpen IN-VB-S-V 6-90Технические характеристики -
SPECK Pumpen IN-VB-S-V 6-90Инструкция по эксплуатации -
SPECK Pumpen IN-VB-S-V 6-80Технические характеристики -
SPECK Pumpen IN-VB-S-V 6-80Инструкция по эксплуатации -
SPECK Pumpen IN-VB-S-V 6-70Технические характеристики -
SPECK Pumpen IN-VB-S-V 6-70Инструкция по эксплуатации -
SPECK Pumpen IN-VB-S-V 6-60Инструкция по эксплуатации -
SPECK Pumpen IN-VB-S-V 6-60Технические характеристики -
SPECK Pumpen IN-VB-S-V 6-50Технические характеристики -
SPECK Pumpen IN-VB-S-V 6-40Технические характеристики -
SPECK Pumpen IN-VB-S-V 6-40Инструкция по эксплуатации -
SPECK Pumpen IN-VB-S-V 6-30Технические характеристики
Узнайте, как правильно отключить и сохранить насосное оборудование для предотвращения повреждений. Следуйте инструкциям по обслуживанию и хранению.