Daikin REYQ14PY1B [200/477] Operation when power is turned on

Daikin REYQ16PY1B [200/477] Operation when power is turned on
Test Operation SiBE37-701_B
189 Test Operation
1.3 Operation when Power is Turned On
1.3.1 When Turning On Power First Time
The unit cannot be run for up to 12 minutes to automatically set the master power and address
(indoor-outdoor address, etc.).
Status
1.3.2 When Turning On Power the Second Time and Subsequent
Tap the RESET button on the outdoor unit PCB. Operation becomes possible for about 2
minutes. If you do not push the RESET button, the unit cannot be run for up to 10 minutes to
automatically set master power.
Status
1.3.3 When an Indoor Unit or Outdoor Unit has been Added, or Indoor or
Outdoor Unit PCB has been Changed
Be sure to push and hold the RESET button for 5 seconds. If not, the addition cannot be
recognized. In this case, the unit cannot be run for up to 12 minutes to automatically set the
address (indoor-outdoor address, etc.)
Status
Outdoor unit Test lamp H2P .... Blinks
Can also be set during operation described above.
Indoor unit If ON button is pushed during operation described above, the "UH"
malfunction indicator blinks.
(Returns to normal when automatic setting is complete.)
Outdoor unit Test lamp H2P .... Blinks
Can also be set during operation described above.
Indoor unit If ON button is pushed during operation described above, the operation lamp
lights but the compressor does not operate. (Returns to normal when
automatic setting is complete.)
Outdoor unit Test lamp H2P .... ON
Can also be set during operation described above.
Indoor unit If ON button is pushed during operation described above, the "UH" or "U4"
malfunction indicator blinks. (Returns to normal when automatic setting is
complete.)
Switch box cover
Service cover
[Service Precautions] label
Lift this protruding
portion to open the
inspection door
EL. COMPO.
BOX cover
LED (H1~8P)
Push button
switch (BS1~5)
Inspection door
DIP switch2
(DS2-1~4)
DIP switch1
(DS1-1~4)
Switch box
(the upper right)
(V0847)
Caution When the 400 volt power supply is applied to "N" phase by mistake,
replace Inverter PCB (A2P) and control transformer (T1R, T2R) in
switch box together.