Chapter 7 Reliability Configuration
7-38
A
B
C
D
Sub-ring 3
Sub- ring 2
G
F
H
E
When the sub ring 3 is changing, it should notify ring 1 and ring 2. The node on the
major ring will run flush FDB. The topology changing of the major ring 1 and ring 2 will
not affect the sub ring 3. Other, the topology changing of the major ring 1 and ring 2 will
not affect each other either.
2. The interconnection ring model without virtual channel
Change the way to understand the ring network as shown in Fig 7-19: ring 1 is the
major ring and it is made up with the ring nodes A, B, G, H and the links of them. When
ring 1 is health, it will block the link between nodes A and B. ring 2 is sub ring, it is made
up with the ring nodes C, D, E, F and the links of C-D, D-E and E-F. When ring 2 is health,
it will block the link between node C and D. ring 3 is another sub ring, it is made up with
the nodes B, C, F, G and the links of B-C, C-F and F-G. When ring 3 is health, it will block
the link of B-C. B-G links are the interconnection links of ring 1 and ring 3 and it belongs
to ring 1. C-F links are the interconnection links of ring 2 and ring 3 and it belongs to ring
3. Ring 1 is the close ring network; ring 2 and ring 3 are not the ring network.
Figure 7-19 the interconnection ring topology without virtual channel
Although ring 2 and ring 3 are not ring network neither, the erps packets of these two
sub ring need to be transmitted to all ring nodes. So, the block link should still transmit
erps protocol packets if the links of B-C and C-D are blocked, and the nodes B, C and C,
D of the block link should also receive and send the erps protocol packets.
When the sub ring 3 is changing, it should notify ring 1. The node on the major ring
will run flush FDB. The topology changing will not affect the sub ring 2. When the sub ring
2 is changing, it will affect the sub ring 3 and the major ring 1. The node on the major ring
should run flush FDB. But, the topology changing of the major ring 1 will not affect the
sub ring 2 and ring 3.
7.5.1.3 ERPS Application
ERPS is used for ring network and it is located in convergence layer, the
convergence loop can complete the layer2 convergence of business; insert the layer3