Daikin EKHWP500A [18/24] X start up and taking out of service

Daikin EKHWP500A [18/24] X start up and taking out of service
4 x Start-up and taking out of service
Installation instructions
18
EKHWP300/500A
Hot water storage tank for air-water heat pumps and solar panels
4PW55928-1
4 Start-up and taking out of service
4.1 Initial start-up
Requirements
The EKHWP300/500A hot water storage tank is erected and fully connected up.
–The heating and hot water system are filled and pressurised to the correct pressure.
The EKHWP300/500A hot water storage tank is filled to the overflow point.
Solar system: All hydraulic and electrical connections have been established in accordance with the installation
instructions.
Checks before start-up
Check all connections for leaks.
Start-up
Check all the points on the enclosed checklist. Make a record of the test results and sign it, together with the operator.
Switch on the EKHBRD* heat pump and start and configure the hot water generation mode (see the EKHBRD* operating and
installation instructions).
Only if all points on the checklist can be answered with Yes may the EKHWP300/500A be started up.
Check list for start-up
1. Is the hot water storage tank properly installed in accordance with a permitted set-up variant and without any discernible damage? Yes
2. Is the storage tank is filled with water to the overflow point? Yes
3. With restoration: Has the heat distribution network been cleaned? Yes
4. Is the safety overflow connection connected to an open drain? Yes
5. Is the water pressure in the system < 6 bar? Yes
6. Has the heating circuit been bled? Yes
7. Are all hydraulic connections tight (leaks)? Yes
8. Does the installation operate without faults? Yes
9. In the case of new installations: Has the operating manual been handed over, and has the owner been instructed? Yes
Location and Date: Signature of installer:
Signature of owner: