Graco Python XL 3/4" [13/48] Calibrate chemical dosage

Graco Python XL 5/8
Operation
3A3948B 13
Prime the Pump
1. Verify all connections and fluid lines are tight.
2. In order to prime the pump, turn the prime valve
(107) counter-clockwise.
NOTE: The pressure regulator and inlet pneumatic nee-
dle valve both effect the pump cycle rate. After inlet
pressure is set, the needle valve can serve as a speed
control.
3. Adjust pneumatic regulator to desired pressure. See
Minimum Pneumatic Pressures by Fluid Plunger
Size and Outlet Pressures on page 10.
4. Open bleed-type pneumatic valve. Slowly turn pump
needle valve counter-clockwise, increasing air/gas
flow to the pump.
5. Keep the pump cycle rate less than 1 cycle every 3
seconds. The pump is primed when discharge from
the prime valve (107) has transitioned from air, to
bubbly liquid chemical, to pure liquid chemical.
6. Close the prime valve (107) tightly and verify that
fluid has stopped draining from the port.
Calibrate Chemical Dosage
1. Begin the process by setting the pump to an esti-
mated setting of the flow rate. See Baseline Chem-
ical Dosage Settings, page 15, for tables of cycles
per minute (CPM), and corresponding gallons per
day (GPD) and liters per day (LPD).
2. Follow the instructions provided with your calibration
gauge in conjunction with the Baseline Chemical
Dosage Settings on page 15.
3. Adjust the cycle rate with the inlet pneumatic needle
valve and/or the pressure regulator.
4. Repeat the test procedure to verify your changes.
Repeat as necessary until the desired flow rate is
achieved.
NOTICE
Pump runaway may occur if the needle valve is
opened too far for pressure settings, causing damage
to the packing seals (103).