Daikin EWAD650BJYNN/Q [312/346] Prestart system checklist

Daikin EWADC14BJYNN [312/346] Prestart system checklist
Prestart System Checklist ESIE07-04
3–56 Part 3 – Troubleshooting
3
1
3
4
5
12.2 Prestart System Checklist
Yes No N/A
Chilled water
Piping complete
Water system filled, vented
Pump installed, (rotation checked), strainers cleaned
Controls (3 way valves, face and bypass dampers, bypass valves, etc)
operable
Water system operated and flow balanced to meet unit design require-
ments
Heat recovery condensers
Piping and headers complete
Water system filled, vented
Temperature sensors installed in the water pockets
Pump installed, (rotation checked), strainers cleaned
Controls (3 way valves, face and bypass dampers, bypass valves, etc)
operable
Water system operated and flow balanced to meet unit design require-
ments
Electrical
Power leads connected to starter
All interlock wiring compete between control panel and complies with
specification
Pump starter and interlock wired
Wiring complies with local codes
Miscellaneous
Thermometer wells, thermometers, gauges, control wells, controls, etc.,
installed
Minimum system load of 60% or machine capacity available for testing
Adjusting controls