Daikin RXQ26MAY1 [124/344] Part 5 test operation

Daikin RXQ46MAY1 [124/344] Part 5 test operation
Si39-501
Test Operation 113
Part 5
Test Operation
1. Test Operation ....................................................................................114
1.1 Procedure and Outline .........................................................................114
1.2 Operation When Power is Turned On ..................................................118
2. Outdoor Unit PC Board Layout ...........................................................119
3. Field Setting ........................................................................................120
3.1 Field Setting from Remote Controller ...................................................120
3.2 Field Setting from Outdoor Unit............................................................133