Daikin FCQ71B7V3B [271/381] Removal of switch box

Daikin FCQ35B7V1 [271/381] Removal of switch box
ESIEN05-04 Disassembly and Maintenance
Part 5 Disassembly and Maintenance 5–31
3
5
1
5
1.11.6 Removal of Switch Box
Warning Be sure to wait 10 minutes or more after turning off all power supplies before disassembling work.
Procedure:
Step
Procedure Points
1
Remove the 2 mounting
screws on the switch
box cover.
2
Remove the 1 mounting
screw on the terminal
block cover.
3
Disconnect each
connector
(7 connectors in total)
connected to the inside
of the switch box.
Q Transfer connector x
3 pieces
Q Direct connector x 4
pieces
Switch box cover
Terminal block box
cover
remote control
Moisture sensor
Heat exchanger
temperature
thermistor
Float switch
Drain pump
Swing motor
For power
supply
connection
Swing motor
Moisture sensor
remote control