Part 4 – Commissioning and Test Run 4–5
3
4
5
1
1.3 General Checks
Checklist The table below contains the general checklist.
Step Check whether...
1 There is external damage.
2 The unit is properly supported and/or has a proper foundation.
3 The unit is installed horizontally with a deviation of maximum 1°.
4 Anti-vibration pads are required.
5 Check for remaining metal dust of burrs. Metal dust or burrs from grinding or drilling in the
metal parts during construction facilitates the rust process and shortens the lifetime of the
unit.
6 The operator has received the operation manual.
7 The installer has received the installation manual.
8 The air volume over the coil is adequate; there is no blockage (from paper, plastic...) or air
short circuit due to wrong positioning.