Daikin FXSQ40P7VEB [152/370] Check operation

Daikin FXSQ32PVE4 [152/370] Check operation
Test Operation SiBE311209
143 Test Operation
1.4 Check Operation
Make sure to carry out the check operation after the first installation. Otherwise, the error
code "
U3
" will be displayed on the remote controller and normal operation cannot be carried
out. When the check operation is finished normally, normal operation can be carried out after
approx. 5 minutes.
<In case of Single system>
Settings and display confirmations are to be made at the el. compo. box.
<In case of Multi system>
Check the settings and display results on the main remote controller.
In case the unit is operated with the leak detection function available:
the outdoor air temperature must be 0°C DB~43°C DB
the indoor temperature must be 10°C DB~32°C DB
In case the unit is operated out of the temperature range as instructed above, the display of
the remote controller shows "
U3
" and the unit operates without the availability of the leak
detection function.
In the check operation, the following checks and judgement will be performed:
Check of the stop valve opening
Check for wrong wiring
Check of refrigerant overcharge
Initial refrigerant detection
In case the leak detection function is available, the check operation will last 2 hours,
otherwise it takes between 40 and 60 minutes to complete the check operation.
Abnormalities on indoor units can not be checked for each unit individual. After the check
operation is finished, check the indoor units one by one by performing a normal operation
using the remote controller.
1.4.1 Procedure of Check Operation
1. Close all front panels except the front panel of the el. compo. box.
2. Turn ON the power to the outdoor unit and the connected indoor units.
Be sure to turn ON the power 6 hours before operation in order to have power running to the
crankcase heater and to protect the compressor.
3. Make the field setting as described in the paragraph "3.2 Field Setting from Outdoor Unit" on
P.162.
4. Press the BS1 MODE button once, and set to the SETTING MODE (H1P LED = OFF).
5. In case the leak detection function is required,
press and hold the BS4 TEST button down for 5 seconds or more. The unit will start the test
operation.
In case the leak detection function is not required,
go into setting mode 2 by pressing the
BS1 MODE
button for 5 seconds. The H1P LED is ON
k
.
Perform following steps.
1) Press the BS2 SET button 3 times.
2) Press the BS3 RETURN button once to confirm.
3) Press the BS2 SET button in order to change the LED display to the following display.
4) Press the BS3 RETURN button once to confirm.
5) Press the BS3 RETURN button a second time to start the test operation. The unit will
start the test operation.
H1P H2P H3P H4P H5P H6P H7P
khhhhkk
H1P H2P H3P H4P H5P H6P H7P
khhhhhl
H1P H2P H3P H4P H5P H6P H7P
khhhhlh