Test Operation SiBE37-704_A
199 Test Operation
5. Press the BS3 RETURN button a second time to start the test operation. The unit will
start the test operation.
The test operation is automatically carried out in cooling mode, the H2P LED will light up
and the messages "Test operation" and "Under centralized control" will display on the
remote controller.
It may take 10 minutes to bring the state of the refrigerant uniform before the compressor
starts.
During the test operation, the refrigerant running sound or the magnetic sound of a
solenoid valve may become loud and the LED display may change, but these are not
malfunctions.
During the test operation, it is not possible to stop the unit operation from a remote
controller. To abort the operation, press the BS3 RETURN button. The unit will stop after
±30 seconds.
6. Close the front panel in order to let it not be the cause of misjudgement.
7. Check the test operation results by the LED display on the outdoor unit.
8. When the test operation is fully completed, normal operation will be possible after 5 minutes.
Otherwise, refer to "Correcting after abnormal completion of the test operation" on page 199
to take actions for correcting the abnormality.
Correcting after abnormal completion of the test operation
The test operation is only completed if there is no malfunction code displayed on the remote
controller. In case of a displayed malfunction code, perform the following actions to correct the
abnormality:
Confirm the malfunction code on the remote controller
H1P H2P H3P H4P H5P H6P H7P
Normal completion
hhkhhhh
Abnormal completion
hkkhhhh
Installation error Error code Remedial action
The stop valve of an outdoor
unit is left closed.
E3
E4
F3
F6
UF
Open the stop valve.
The phases of the power to the
outdoor units are reversed.
U1
Exchange two of the three phases (L1, L2, L3)
to make a positive phase connection.
No power is supplied to an
outdoor or indoor unit
(including phase interruption).
LC
U1
U4
Check if the power wiring for the outdoor units
are connected correctly.
Incorrect interconnections
between units
UF
Check if the refrigerant line piping and the unit
wiring are consistent with each other.
Refrigerant overcharge
E3
F6
UF
Recalculate the required amount of refrigerant
from the piping length and correct the
refrigerant charge level by recovering any
excessive refrigerant with a refrigerant recovery
machine.
Insufficient refrigerant
E4
F3
Check if the additional refrigerant charge has
been finished correctly.
Recalculate the required amount of refrigerant
from the piping length and add an adequate
amount of refrigerant.
The added amount of
refrigerant was not inputted
after automatic charging.
PF
Availability of the leak detection function feature
requires input of the additional refrigerant
charge amount immediately after finishing the
automatic charging. Refer to " 1.2.6.6
Procedure for inputting the additional
refrigerant charge weight into the PCB" on
page 191.
In case the test operation was
interrupted or the unit was
operating out of the instructed
temperature range, the initial
refrigerant detection has
failed.
U3
In case the test operation was interrupted,
perform the test operation again.
In case the unit was operating out of the
instructed temperature range, the unit can still
be operated normally, but the leak detection
function will not be available.
Perform the test operation again within the
instructed temperature range.