Daikin RWEYQ26PY1 [113/342] Check operation

Daikin RWEYQ30PY1 [113/342] Check operation
Test Operation Si30-813
102 Test Operation
1.1.3 Check Operation
(For the operation to be done for the first time after installation, you need to perform a checking
operation according to this guideline without fail. Otherwise, Abnormal Code “U3” appears and
normal operation cannot be carried out.)
(1) Check the connection of interlock circuit The outside unit cannot be operated if the
interlock circuit has not been connected.
(2) As necessary, configure the system settings
onsite by using the dip switch (DS1) and push
button switches (BS1 to 5) on the outside unit
PC board (A1P).
After this, close the cover of electrical box.
Always perform configuration after turning ON the
power. To learn the setting method, refer to the
[Service Precautions] label attached at the cover
of electrical box shown in the figure 27.
Remember, the actual set-tings you have made
must be recorded on the [Service Precautions]
label.
(3) Turn ON the power to the outside units and
indoor units.
Make sure to turn ON the power 6 hours before
starting the operation. This is necessary to warm
the crankcase by the electric heater.
(4) Start the heat source water pump and fill the
heat source water in the outside unit.
The outside unit cannot be operated if the heat
source water pump is not running.
(5) Make sure that the temperature of heat
source water is kept within the operation
range (10 - 45°C).
The outside unit cannot be operated at a
temperature outside the operation range.
(6) Check the LED on the PC board (A1P) in the outside unit to see if the data transmission is
performed normally.
(7) • Using the push button switches (BS1 - 5) on
the P-panel (A1P) of outside unit, carry out a
local setting, if necessary.
• In case of an installation of multiple outside
units, carry out the setting on the master
unit.
(Setting on the slave unit becomes invalid.)
Always carry out the setting only after the power
supply has been applied.
For the method of setting, refer to the label of
“Points to be noted when providing services
attached to the cover of electrical box (shown in
the figure 27) of the outside unit.(After setting,
record the details of that setting to the label of
“Points to be noted when providing services
without fail.)
(8) Check all shutoff valve is opened.
If some shutoff valve is closed, open them.
(Refer to “9-10 Shutoff valve operation
procedure”.)
[CAUTION]
Do not leave any shutoff valve closed.
Otherwise the compressor will fail.
For Heat recovery system of cooling and heating:
Open all stop valves on the suction side,
discharge gas side and liquid side.
For cooling and heating switching operation
system:
Open the stop valves on discharge gas side and
liquid side. (Keep the stop valve on suction
side fully closed.)
(9) Perform the check operation following the
instructions printed on the [Service
Precautions] label.
If you push the test run button (BS4) on the P-
panel (A1P) of the outside unit.
for 5 seconds, the test run starts.
If you want to interrupt the test run, push the
RETURN button (BS3) on P-panel (A1P) of the
outside unit. The system continues residual
operation for about 1 minute (maximum 10
minutes) and then stops.
(During test run, you cannot stop it by a command
from a remote controller.)
You need to perform the above settings on the
PC board by accessing the PC board through
the inspection cover on the switch box cover.
LED display
(Default status
before delivery)
One outside unit installed
When multiple
outside unit
installed (
)
Master station
Sub station 1
Sub station 2
Microcomputer
operation
monitor
Page
HAP H1P H2P H3P H4P H5P H6P H7P H8P
Ready/
Error
Cooler/heater changeover
Individual
Bulk
(parent)
Bulk
(child)
Low
noise
Demand
Multi
LED display: OFF ON Blinking
() The master unit is the outside unit to which the transmission wiring for the
indoor units is connected. The other outside units are sub units.