Daikin RWEYQ28PY1 [111/342] Test operation

Daikin RWEYQ28PY1 [111/342] Test operation
Test Operation Si30-813
100 Test Operation
1. Test Operation
1.1 Procedure and Outline
Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check Work Prior to Turn Power Supply On
1.1.2 Turn Power On
Check on refrigerant piping, water
piping and piping insulation
Check on amount of additional
refrigerant charge
Check on air tight test and
vaccume drying
Check on stop valves opening
Check the below items.
• Power wiring
• Control transmission wiring
between units
• Operation signal to heat
source pump and interlock
wiring from pump
• Interlock circuit
• Earth wire
{ Is the wiring performed as specified?
{ Are the designated wires used?
{ Is the grounding work completed?
Use a 500V megger tester to measure the insulation.
Do not use a megger tester for other circuits than 200V (or
240V) circuit.
{ Are the setscrews of wiring not loose?
{ Is pipe size proper? (The design pressure of this product is
4.0MPa.)
{ Are pipe insulation materials installed securely?
Liquid and gas pipes need to be insulated. (Otherwise causes
water leak.)
{ Is refrigerant piping carried out correctly as per installation
manual?
(Special care is required for multi-outside unit installation.)
{ Is the air tight test and vaccume drying carried out as per
installation manual?
{ Is refrigerant charged up to the specified amount?
If insufficient, charge the refrigerant from the service port of stop
valve on the liquid side with outside unit in stop mode after turning
power on.
{ If the specified amount of refrigerant can not be charged in stop
mode, charge the required refrigerant as per "Additional refrigerant
charge mode" in operation. (Refer page 142)
{ Has the amount of refrigerant charge been recorded on “Record
Chart of Additional Refrigerant Charge Amount”?
{ Check to make sure the all stop valves on outside units are open.
Turn outside unit, indoor unit,
BS unit and heat source water
pump power on.
Confirm LED display on
outside unit's PC board
Carry out field setting on
outside unit PC board
{ Be sure to turn the power on 6 hours before starting operation to
protect compressors. (to power on clankcase heater)
{ Make sure the display is normal.
Following table shows correct display.
{ For field settings, refer to “Field Settings” on and after P122.
After the completion of field settings, set to “Setting mode 1”.
In case of multi-outside unit connection, carry out the field settings
on master unit. (The setting on slave unit is not effective.)