Daikin RXYQ10PY1 [271/487] Leading wire procedure

Daikin RXYQ22PY1 [271/487] Leading wire procedure
ED34-645B Field Wiring
Installation of Outdoor Units 663
15
7.3 Leading Wire Procedure
The power wiring and ground wiring are passed out from the power wiring hole on the sides, the front (knock hole)
or the bottom frame (knock hole).
The transmission wiring is passed out from the wiring hole (knock hole) on the front of the unit or from a piping
hole.
1. Electrical wiring diagram
2. On the back of the EL.COMPO. BOX lid.
3. Power wiring, ground wiring (inside conduit)
4. (When the wiring is routed out through the side panel.)
5. Transmission wiring
6. Pipe opening
7. Conduit
8. For power wiring and ground wiring
9. Through cover
10.Cut off the shaded zones before use.
11.Burr
12.Knockout hole
13.For transmission wiring
Open the knock holes with a hammer or the like.
After knocking out the holes, we recommend you paint the edges and areas around the edges using the repair
paint to prevent rusting.
When passing wiring through the knock holes, remove burrs around the knock holes and protect the wiring with
protective tape. (Refer to figure *)
If small animals might enter the unit, block off any gaps (hatching parts in figure 20) with material (field supply).
1
2
10
9
8
7
3
11
12
8
12
13
5
6
4
Note

Содержание