Daikin REYQ16PY1B [167/477] Installation process

Daikin REYQ16PY1B [167/477] Installation process
SiBE37-701_B Test Operation
Test Operation 156
1. Test Operation
1.1 Installation Process
Below Figure shows the installation process. Install in the order of the steps shown.
3. Selection of Location
4. Inspecting and Handling the Unit
5. Placing the Unit
7. Field Wiring 6. Refrigerant Piping
8. Air Tight Test and Vacuum Drying
9. Pipe Insulation
10. Checking of Device and Installation Conditions
11. Additional Refrigerant Charge and Check Operation
13. Test Run
Operations which require the
power to be turned on.